With a force majeure notice, Oracle hedges against Project Jupiter running late
Oracle shares fell more than 6% on Thursday after it sent a force majeure notice to Blue Owl over Project Jupiter, its New Mexico AI data center. The notice protects Oracle's cash if the site runs late and makes its 2028 date the one lenders and investors now watch.
The Board Room · Leadership desk
What happened
- Sources told Bloomberg that Oracle is not trying to leave as primary tenant but could try to delay payments if the project slips before 2028, though it is unclear whether that would work.
- Oracle vice president Michael Egbert said the project remains on its planned schedule and that he is confident in moving forward.
- Blue Owl said it, STACK Infrastructure and Oracle remain fully aligned, and that the notice does not change the project's financial commitments.
- Project Jupiter is part of the $500 billion Stargate Project that OpenAI, Oracle and SoftBank launched last year.
Why it matters
- Who's exposed exposure If Oracle's deferral argument holds, Blue Owl and whoever finances the developer wait for rent through any delay before 2028, while Oracle's cash stays protected.
- What it sets up precedent Oracle calls such notices routine at this scale; if developers accept that, tenants on other large AI sites can be expected to reserve the same delay rights, and leases will be priced with that in mind.
- Who has to decide decision Companies planning on Jupiter capacity, OpenAI among its intended users, now hold a 2028 date their landlord's tenant has hedged in writing, and have to decide how much schedule slack to carry.
Next story · Invest · Sep 28
Oracle's force majeure notice on Jupiter tests who pays when AI campuses run lateConfirmed10 publishers
Force majeure is usually invoked when a company faces an earthquake, a storm or another event beyond its control [4]. Oracle has sent one while saying the project is on schedule [6], to keep open an argument that its payments can wait if the building is late [2]. Evercore called the notice "a pretty sensible move" for aligning Oracle's revenue and expenses if the project is delayed, and said it "is not an indication that this project is going away" [12].
RBC Capital Markets analyst Rishi Jaluria made the skeptic's case. The notice "signals the company's own risk assessment on execution has shifted enough to warrant legal cover," he wrote [19]. Oracle's reply came from vice president Michael Egbert. "Force-majeure notices are commonplace in developments of this scale and are often used to preserve contractual rights among project partners. They do not, by themselves, establish a project delay or change delivery expectations," he said [5].
Both statements can be true at once. A tenant can expect to hit its date and still judge that the risk of missing it has grown enough to justify a written claim. Oracle took protection on payments at the cost of a public signal about execution, and its shares were still down 4.4% around midday on Thursday [3].
The board-deck version comes from William Blair: the immediate financial impact should be limited, because Project Jupiter is not expected to contribute revenue in Oracle's current fiscal year [13]. That holds for this year's income statement and leaves out the spending. Oracle reported $28.5 billion of first-quarter capital expenditure, up from $8.5 billion a year earlier, roughly 3.4 times as much [18], and kept its fiscal 2027 capex forecast at $90 billion to $95 billion [14]. That money turns into revenue only when new capacity comes online and converts contract backlog [17]. "Any slippage in the 2028 timeline has direct implications for capacity delivery and revenue recognition given Oracle's supply-constrained posture," Jaluria wrote [20].
This quarter's notice sets up next quarter's financing questions. Oracle secured $18 billion in bank loans for the project, Bloomberg reported last year [15]. Business Insider has reported that some banks and institutional investors grew wary of exposure to Oracle as lenders tried to distribute debt tied to its Stargate data centers [16]. I'd expect those lenders to ask which events Oracle considers beyond its control. The site's known troubles are local. It survived legal challenges that reached New Mexico's Supreme Court [9], and it has drawn protests and lawsuits over its environmental impact and transparency [11]. Recent polling cited by Forbes found a majority of voters from both parties oppose further data center construction [21].
For operators, the record shows a tenant hedging a date. Oracle is reserving the right to pay later if the building is late while staying on as primary tenant [2], at a site meant to host AI infrastructure for companies including Oracle and OpenAI [10]. The reports do not say what event, if any, the notice cites.
What to watch
- Whether Oracle or Blue Owl discloses which event the notice cites, and whether the developer accepts that payments can be deferred.
- Oracle's next quarterly update on the 2028 timeline for Project Jupiter and on its $90 billion to $95 billion fiscal 2027 capex forecast.
- Terms on the next distribution of Stargate-linked debt, given reported lender wariness about Oracle exposure.
Clarity's read
What the record supports and how the coverage leans. The claims behind it follow.
Reality
- Evidence62
- Adoption
- Not scored
- Hype gap+20
- Incentives60
- Confidence60
Perspective Coverage
3 publishers- Builder
- Builder 7%
- Operator
- Operator 40%
- Investor
- Investor 53%
Claim ledger
Ranked by verification strength, evidence, and original report placement.
- [1]
Oracle sent a force majeure notice to Blue Owl Capital, the company that owns the primary developer of Project Jupiter, a data center in Dona Ana County, New Mexico, according to sources who spoke to Bloomberg.
- [2]
Oracle is not trying to leave as the primary tenant of the site but could attempt to delay payments should the project be delayed before 2028; it is unclear whether this tactic would work.
- [3]
Oracle's stock fell over 6% after markets opened on Thursday and was still down 4.4% around 12:30 p.m. EDT.
- [4]
Force majeure is usually used when companies face extreme circumstances beyond their control like an earthquake, storm or other natural disaster.
- [5]
"Force-majeure notices are commonplace in developments of this scale and are often used to preserve contractual rights among project partners. They do not, by themselves, establish a project delay or change delivery expectations," Oracle vice president Michael Egbert said.
- [6]
Oracle vice president Michael Egbert said the project "remains on our planned schedule" and that he was "confident" in moving forward with the New Mexico project.
- [7]
"Blue Owl, STACK Infrastructure and Oracle remain fully aligned on Project Jupiter," a Blue Owl spokesperson wrote. "This notice does not change the financial commitments to this multiyear project."
- [8]
Project Jupiter is part of the $500 billion Stargate Project launched by OpenAI, Oracle and SoftBank last year.
- [9]
The New Mexico facility already survived legal challenges that reached the state's Supreme Court.
- [10]
Project Jupiter is intended to host artificial intelligence infrastructure for companies like Oracle and OpenAI.
- [11]
The data center has spurred protests, lawsuits and fierce pushback over concerns about its environmental impacts and transparency.
- [12]
Evercore called the reported notice "a pretty sensible move" to align Oracle's revenue and expenses if the project is delayed and said it "is not an indication that this project is going away."
- [13]
William Blair said the immediate financial impact should be limited because Project Jupiter is not expected to contribute revenue in Oracle's current fiscal year, though investors will remain focused on whether delays to AI data centers push back future cloud revenue.
- [14]
Oracle reported $28.5 billion in first-quarter capital expenditures, up from $8.5 billion a year earlier, and maintained its fiscal 2027 capital expenditure forecast at $90 billion to $95 billion.
- [15]
Oracle previously secured $18 billion in loans from multiple banks for the project, Bloomberg reported last year.
- [16]
Business Insider previously reported that some banks and institutional investors were growing wary of taking on too much exposure to Oracle, as lenders sought to distribute debt tied to its Stargate data centers.
- [17]
Oracle's strategy depends not only on signing customers but also on bringing enough new capacity online to convert its growing backlog of contracts into revenue.
- [18]
Oracle's first-quarter capital expenditure was roughly 3.4 times the level of a year earlier.
- [19]
RBC Capital Markets analyst Rishi Jaluria wrote that the notice "signals the company's own risk assessment on execution has shifted enough to warrant legal cover."
- [20]
"Any slippage in the 2028 timeline has direct implications for capacity delivery and revenue recognition given Oracle's supply-constrained posture," Jaluria wrote.
- [21]
Recent polling has found a majority of voters from both parties oppose further data center construction.
Sources
3 independent publishers whose own reporting we read for this story.
- businessinsider.comOracle's 'force majeure' notice raises questions about the company's ability to deliver on AI data centers
1 article · September 24, 2026
- forbes.com.auOracle stock slides after company issued ‘force majeure’
1 article · September 24, 2026
- Oracle sends 'force majeure' notice to Project Jupiter developers to protect itself from liability | Las Cruces Local News | The Las Cruces New Mexican | santafenewmexican.com
santafenewmexican.com