Sesterce wants a closed Finnish paper mill's power and water for a 600MW AI campus

Sesterce plans a 600MW AI campus at the shut Kaipola paper mill in Jämsä, Finland, with building on a 200MW first phase due this year. Buyers of European AI capacity get a site with grid and water already connected, though no date yet for booking it.

The Product Desk

Send a correction

What happened

  • Sesterce, a French company, puts the investment at 10bn, given in euros by The Next Web and in dollars by DatacenterDynamics.
  • Kaipola Green Port bought the mill site from UPM in 2021, and its board chair told Yle that talks to sell the whole site to Sesterce are well underway.
  • Local officials in Jämsä welcomed the project but noted that permits are still required.
  • Sesterce says it has already secured an unnamed anchor customer for the campus, according to DatacenterDynamics.
  • Sesterce pledges to enable 1MW of new renewable generation on the Finnish grid for every MW the campus consumes, within 10 years of opening.

Why it matters

  • Who has to decide decision A second buyer at Jämsä competes for what the anchor customer leaves of the 200MW first phase, so the uncommitted share is the figure to get from Sesterce before shortlisting it.
  • What doesn't add up contradiction The renewable pledge's clock starts at first operation in one report and now in the other, so a buyer counting on matched clean power could be off by the length of construction.
  • What it limits constraint Controllable, flexible power consumption means the campus can draw less at times, and tenants running long training jobs need the terms for those cuts written into their contracts.
  • What it sets up precedent A built-up mill site avoids the forest clearing a Finnish regulator halted at two Google sites, so more Finnish AI builds are likely to target old industrial land, as Sesterce's gigawatt plan already does.

An infrastructure lead with a shortlist of European GPU suppliers sees a French operator promising more than a gigawatt in Finland [1][5], and has to decide whether Jämsä goes on the list. On the two reports, it belongs on the list of projects to track.

Here is what Sesterce is pitching: more than 1GW of AI capacity on existing Finnish industrial sites, built in line with demand, The Next Web reported [5]. Here is what has been scheduled. Phase one, at 200MW, is at most a fifth of that goal [17]. Phase two would triple it [18]. The anchor customer in Sesterce's statement [9] means any second buyer starts the first phase with someone ahead of them in the queue.

Sesterce's argument for the mill is its hookups. "Our goal is to preserve the area's industrial identity while making use of existing infrastructure, including the power grid, water systems, buildings and logistics connections," chief executive Youssef El Manssouri said [6]. UPM shut the mill in early 2021 [3]. Jämsä's mayor, Jori Reijula, called the project "an interesting opportunity to strengthen the vitality of the region, provided it progresses from plans to implementation and meets the applicable requirements" [8].

Reused connections should make a build faster than clearing new land, and Finland has a current example of what new land runs into. Google, which said in September it would spend €13bn on Finnish AI infrastructure in 2027 and 2028, was ordered by a Finnish regulator this week to stop clearing forest at two planned sites [21][22]. I'd expect a built-up mill site to avoid that dispute. Neither report gives an energisation date for the first 200MW, so the speed advantage has no number on it yet.

The renewable pledge comes in two versions. In DatacenterDynamics' account, Sesterce commits to "enabling" a megawatt of new renewables for each megawatt consumed, within 10 years of the campus becoming operational [10]. The Next Web gives the window as the next ten years [11]. The gap between those two clocks is the construction period. The reports also split on currency: €10bn against $10bn for the campus, and €10 million against $10 million for the community fund [1][2][12][13].

Cooling is a closed-loop liquid system topped up with harvested rainwater and recycled water [19]. El Manssouri also said the campuses will "feature controllable and flexible power consumption" [20]. A tenant running long training jobs will want the contract to say who decides when that consumption is cut.

The sovereign case rests on ownership. Sesterce is French [1]. Its other gigawatt project, a campus in Bosquel in northern France, is a June agreement with SoftBank Group [14], and it announced a $471m AI data centre in Valence last year [15]. A buyer who only needs an EU-headquartered operator has that answer now. A buyer whose rules extend to co-investors and anchor tenants has more questions to put to Sesterce.

The test I'd apply to Jämsä, and to the next conversion of an old industrial site, is a 2x2. One axis is whether the site has changed hands and cleared permits. The other is whether capacity has a delivery date for a customer other than the anchor. A project with both can be priced against greenfield builds. Land settled with no date means a quarterly check-in. A date with no permits is a risk to price into the contract. Neither puts the project on a watch list. On the published record, Jämsä is in that last box: the sale is still being negotiated, permits are pending, and the one customer commitment belongs to the anchor [16][7][9].

What to watch

  • Completion of Kaipola Green Port's sale of the whole site to Sesterce, and the permit decisions Jämsä officials say are still needed.
  • A named anchor customer, and how much of the 200MW first phase it takes.
  • An energisation date for phase one, the first figure that would let buyers compare the mill conversion's speed with greenfield builds.

Clarity's read

What the record supports and how the coverage leans. The claims behind it follow.

Reality

Evidence45
Adoption10
Hype gap+30
Incentives70
Confidence60

Perspective Coverage

3 publishers
Builder
Builder 13%
Operator
Operator 45%
Investor
Investor 42%
Why these scores

Claim ledger

Ranked by verification strength, evidence, and original report placement.

  1. [1]

    French AI infrastructure company Sesterce plans to invest more than €10bn in an AI data centre campus at a former paper mill in Jämsä, central Finland.

    Reported Supported Source: The Next WebView cited source
  2. [2]

    Sesterce has announced plans for a $10 billion AI data center campus in Jämsä, Finland.

    Reported Supported Source: DatacenterDynamicsView cited source
  3. [3]

    The campus will be located on the Kaipola site, where UPM shut down its paper mill in early 2021.

    Reported Supported Source: The Next Web, citing SesterceView cited source
  4. [4]

    Building work on the first phase, with 200MW of capacity, is due to start this year; a second phase would raise capacity to 600MW.

    Reported Supported Source: The Next WebView cited source
  5. [5]

    Over time, Sesterce aims to build more than one gigawatt of AI capacity in Finland on existing industrial sites, in line with demand.

    Reported Supported Source: The Next WebView cited source
  6. [6]

    Our goal is to preserve the area's industrial identity while making use of existing infrastructure, including the power grid, water systems, buildings and logistics connections.

    Reported Supported Source: Youssef El Manssouri, CEO of SesterceView cited source
  7. [7]

    Local officials have welcomed the plan, but they noted that permits are still required.

    Reported Supported Source: The Next WebView cited source
  8. [8]

    The Sesterce project is an interesting opportunity to strengthen the vitality of the region, provided it progresses from plans to implementation and meets the applicable requirements.

    Reported Supported Source: Jori Reijula, Mayor of JämsäView cited source
  9. [9]

    According to Sesterce's statement, the company has already secured an anchor customer for the site.

    Reported Supported Source: DatacenterDynamics, citing Sesterce statementView cited source
  10. [10]

    Sesterce committed to 'enabling' a megawatt of newly built renewable generation capacity on the Finnish power grid for every megawatt the campus consumes within 10 years of the campus becoming operational.

    Reported Supported Source: DatacenterDynamics, citing Sesterce statementView cited source
  11. [11]

    Over the next ten years, Sesterce aims to add one megawatt of new renewable energy to the grid for every megawatt the campus uses.

    Reported Supported Source: The Next WebView cited source
  12. [12]

    Sesterce will set up a €10 million fund to support local projects.

    Reported Supported Source: The Next WebView cited source
  13. [13]

    The company will establish a $10 million community fund to finance local projects in Jämsä.

    Reported Supported Source: DatacenterDynamicsView cited source
  14. [14]

    In June, Sesterce and SoftBank Group agreed to develop a 1GW AI campus in Bosquel, northern France.

    Reported Supported Source: The Next WebView cited source
  15. [15]

    Last year, Sesterce announced a $471m investment to develop an AI data center in Valence, France.

    Reported Supported Source: DatacenterDynamicsView cited source
  16. [16]

    Kaipola Green Port owns the site, having purchased it from UPM in 2021; board chair Martti Inkovaara told Yle that negotiations to sell the entire site to Sesterce are well underway.

    Reported Supported Source: The Next Web, citing YleView cited source
  17. [17]

    The 200MW first phase is at most one fifth of Sesterce's goal of more than 1GW in Finland.

    Derived Supported
  18. [18]

    The second phase would triple capacity from the first phase.

    Derived Supported
  19. [19]

    The site will feature a closed-loop liquid cooling system supplemented with harvested rainwater and recycled water.

    Reported Supported Source: DatacenterDynamics, citing SesterceView cited source
  20. [20]

    The Sesterce Campus projects will use liquid cooling, deliver high energy efficiency, and feature controllable and flexible power consumption.

    Reported Supported Source: Youssef El Manssouri, CEO of SesterceView cited source
  21. [21]

    Google said in September it would spend €13bn on AI infrastructure in Finland in 2027 and 2028.

    Reported Supported Source: The Next WebView cited source
  22. [22]

    This week a Finnish regulator ordered Google to stop clearing forest at two planned sites.

    Reported Supported Source: The Next WebView cited source

Sources

3 independent publishers whose own reporting we read for this story.

  1. channelnewsasia.com

    1 article · October 7, 2026

    France's Sesterce plans $11 billion AI investment in Finland
  2. datacenterdynamics.com

    1 article · October 8, 2026

    Sesterce to invest $10bn in 600MW AI data center campus in Jämsä, Finland
  3. thenextweb.com

    1 article · October 8, 2026

    Sesterce plans €10B AI data centre campus at former Finnish paper mill

Topics and entities

Topics

  • Nordic data centre investment
  • Industrial site reuse for data centres
  • AI Data Centres

Entities