AirTrunk postpones its $1.5 billion Singapore REIT IPO into next year
Blackstone-backed AirTrunk has delayed a Singapore REIT IPO of about $1.5 billion until next year, according to people familiar with the matter. One account blames a chip rout, the other US rate rises; the yield points to rates.
The Investor · Invest desk

Two values for the yield on AirTrunk's planned Singapore REIT: 5.5% as previously envisaged, rising to a roughly 6% yield that AirTrunk considered offering to sweeten the deal.
| Measure | Value | As of | Claim |
|---|---|---|---|
| Previously envisaged yield | 5.5% | 9 | |
| Considered yield, roughly | 6% | 9 |
What happened
- AirTrunk has not set a launch date, and one of the people said the aim is to complete the listing by early next year.
- Nvidia-backed Firmus Grid saw its Australian data centre IPO collapse last week after it failed to draw enough demand at the valuation it sought.
- The data centre unit of Philippine telecoms firm PLDT said last week it would defer its own REIT IPO to next year because of rising interest rates.
- Singapore's main REIT index has fallen 12% since late July.
Why it matters
- What doesn't add up contradiction The two accounts rank the causes differently. A chip rout needs chip stocks to recover before a deal can launch; a yield problem needs borrowing costs to stop rising.
- What it limits constraint AirTrunk will not raise about $1.5 billion from public investors in the September or October window it had planned for.
- What it sets up precedent A yield of roughly 6% was on the table and the deal still stalled. Buyers now have a reference point for the next data centre REIT that comes to Singapore.
Next story · Invest · 4d ago
Firmus Grid pulls $5 billion IPO after asking 2.9 times its valuation of two months earlierConfirmed2 publishers
Chipmakers are the obvious suspect. Asian equities slid to more than two-month lows on Tuesday, led by a rout in chipmakers [13], and ETRealty's report frames the delay as a casualty of that selloff. But the same report closes by listing investors who are reassessing valuations, rising borrowing costs and the durability of AI demand [6], and the other account, from people familiar with the plan, puts higher interest rates and market volatility first [14].
We think rates explain more of the delay, and the yield shows it. REITs are rate-sensitive and come under pressure when borrowing costs are high [16]. AirTrunk had considered offering a yield of roughly 6%, up from the 5.5% it first envisaged [9]. For the same cash distribution, that half point means a unit price 8.3% lower [11]. Applied to a REIT expected to be valued at about $15 billion [18], an 8.3% haircut is roughly $1.25 billion [19], on the assumption that the $15 billion was struck at 5.5%, which neither source confirms. Investors stayed cautious even at the higher yield, the people said, because of September's US rate rise and the prospect of more increases [15].
The raise itself is small against the valuation: $1.5 billion on $15 billion is a 10% slice [12] (or a 10% slice of the equity, if the $15 billion is an equity figure; the sources do not say). The price of that slice will be used to value the remaining 90%. Blackstone and Canada Pension Plan Investment Board paid A$24 billion, or US$16.7 billion, for the company in 2024 [17], so $15 billion sits about 10% below that price [20]. The two numbers are not necessarily like for like.
Firmus is a different trade. According to the second account, its failure reflected investor caution about AI infrastructure deals that hinge on future earnings [8]. We read that as a problem with the valuation multiple, while AirTrunk's is a problem with the yield, so at least two different pricing problems sit behind the three deferrals in about a week.
What would show we have this wrong: the REIT index and US rates steady, and AirTrunk still on the shelf. That would put the weight back on the AI selloff. A launch near the original 5.5% while chip stocks keep falling would say the opposite. AirTrunk did not immediately respond to a request for comment, and Blackstone declined to comment [10].
What to watch
- The next US rate decision, since investors told the people involved that further increases are what keep them cautious.
- Whether PLDT's data centre unit or AirTrunk sets a firm launch date, and at what yield.
Information, not investment advice. This story is general information about companies and markets, drawn from cited reporting. It is not a recommendation to buy, sell or hold any security; check the cited sources before acting.
Clarity's read
What the record supports and how the coverage leans. The claims behind it follow.
Reality
- Evidence58
- Adoption
- Not scored
- Hype gap+15
- Incentives
- Not scored
- Confidence62
Perspective Coverage
3 publishers- Builder
- Builder 7%
- Operator
- Operator 31%
- Investor
- Investor 62%
Claim ledger
Ranked by verification strength, evidence, and original report placement.
- [1]
Blackstone-backed AirTrunk has postponed a Singapore REIT IPO that could raise about $1.5 billion, two people with direct knowledge of the matter said.
- [2]
AirTrunk was originally planning to launch the IPO in September or October but put it on hold due to market conditions.
- [3]
A planned IPO in Australia by another data centre company, Nvidia-backed Firmus Grid, collapsed last week after it failed to bring in enough demand at the valuation it sought.
- [4]
The data centre subsidiary of Philippine telecommunications firm PLDT said last week it would defer its REIT IPO to next year given rising interest rates.
- [5]
Singapore's main REIT Index has tumbled 12% since late July.
- [6]
The postponement follows the scrapping of Firmus' planned IPO, as investors reassess valuations, rising borrowing costs and the durability of demand tied to the AI boom.
- [7]
AirTrunk has not decided when to launch the offering but is aiming to complete the listing by early next year, one of the people said.
- [8]
Firmus's failure reflected growing investor caution about artificial intelligence infrastructure deals that hinge on future earnings.
- [9]
To sweeten the deal, AirTrunk had considered offering a roughly 6% yield for its REIT, up from a previously envisaged 5.5%.
- [10]
AirTrunk did not immediately respond to a request for comment, and Blackstone declined to comment.
- [11]
For the same cash distribution, moving the yield from 5.5% to 6.0% implies a unit price about 8.3% lower.
- [12]
A $1.5 billion raise on a roughly $15 billion valuation is a 10% slice.
- [13]
Asian equities slid to more than two-month lows on Tuesday, led by a rout in chipmakers that renewed investor scrutiny of the AI trade.
- [14]
AirTrunk is delaying the planned Singapore REIT IPO until next year as higher interest rates and market volatility temper investor demand, according to people familiar with the matter.
- [15]
September's interest rate rise in the US and the prospect of further increases mean investors are still cautious, the people said.
- [16]
REITs are rate-sensitive and therefore come under pressure when borrowing costs are high.
- [17]
In 2024, Blackstone and Canada Pension Plan Investment Board acquired AirTrunk for A$24 billion (US$16.7 billion), Blackstone's biggest-ever investment in the Asia Pacific region.
- [18]
The REIT was expected to be valued at about $15 billion.
- [19]
An 8.3% reduction on a $15 billion valuation is roughly $1.25 billion, if the valuation was set at a 5.5% yield (not confirmed by the sources).
- [20]
A $15 billion REIT valuation is about 10% below the US$16.7 billion paid for the company in 2024.
Sources
3 independent publishers whose own reporting we read for this story.
- datacenterdynamics.comAirTrunk to delay IPO amid rising interest rates - report
1 article · October 13, 2026
- AirTrunk IPO Delay: AirTrunk Delays $1.5 Billion Singapore REIT IPO Amid AI Stock Selloff, ETRealty
realty.economictimes.indiatimes.com
1 article · October 13, 2026
- Data centre operator AirTrunk is said to delay US$1.5 billion IPO
sg.finance.yahoo.com
1 article · October 12, 2026
Topics and entities
Topics
- Interest Rates
- Data centre IPOs
- AI infrastructure financing